Posted: Tuesday, October 29th 2013 at 10:44am

Winder is 'wide open' this week

By Ken Stanford Staff
EMAIL STORY CONTACT EDITOR PRINT
WINDER - Georgia DOT announces the around-the-clock double lane closure is no longer in place in Winder. But the major road rebuilding project in downtown is not yet finished.

Curbing and gutter construction will occur in the “bump out” planting areas located in the on street parking along State Route 11. This week the installation of conduit and the bases for the new decorative lighting will continue. Contractors are focusing on the Streetscape portion of the work; new, wider sidewalks, decorative lighting, benches, bike racks, plantings and removing the damaged asphalt parking areas then rebuilding them.

This 0.72 mile long project was awarded to G.P.’s Enterprises of Statham for $4.9 million with a completion date of July 31, 2014. The project will rebuild SR 11/Broad Street from the ground up. Enhancement work includes new sidewalks, curb and gutter, benches, lighting and landscaping.
Associated Categories: Business News, Local/State News

© Copyright 2014 AccessNorthGa.com
All rights reserved. This material may not be published, broadcast, rewritten, or redistributed without permission.


  • Click here
  • Click here
  • Click here
  • Click here
  • Click here
0.040790
icon
53°F
Gainesville, GA 30501
Overcast
Wind: ENE 10 mph
Dew point: 44°F